1. Foundation work
- Foundation work should be done by the customer pursuant to all specifications and considering
  ground durability /stability of the site where the tank is to be located.
- The strength of concrete for the foundation work should have physical properties of over 180Kg/Cm2
- The thickness of mortar for the finishing work on the concrete base should be less than 20 mm

2. Piping Work
We will provide a socket for piping in advance at the designated location. Therefore, the customer should decide the location and the size precisely of the inlet and the outlet for the water overflow valve and drainage before ordering the tank

Precautions in handling



1. Delivery
- Do not put an intensive load or impact in anyway while moving the tank.
  Be sure to use buffers for the part that the tank comes in contact with, such as ropes or while the vehicle is
  moving

2. Piping
- Install a prop while installing piping and take care not to put an excessive load on the diffusers.
- Install pipes on the site where the tank is located and take care not to put on a biased load.
- Take precautions to avoid fire or other occurrences/accidents while welding

3. Maintenance and repair
- If it is not used for a long time, be sure to drain the water from the tank
- As the tank is a reservoir of water for consumption by people, regular inspection should be done for safety